Project Update, June 14
The concrete for the South Abutment has been poured. The North Abutment is being framed and the concrete crew is also tying in the rebar cages. The concrete for the North Abutment should be poured at the end of next week. Our contractor is on schedule to have the trail back open by June 30th.