Project Update, June 21

O’Quinn Construction is pouring the last of the concrete today. They will be installing the handrails, benches, and bike racks next week.

O’Quinn will also be bringing in dirt next week to dress up around the path and bridge. The path could be open the weekend of June 28, but no later than Monday, July 1.

The week of July 1, O’Quinn Construction will begin work on the pier. O’Quinn Construction will build the pier from the barge on site. The construction of the pier will not interfere with the public using the Spanish Moss Trail.

The pier should take one to two weeks to complete, depending on the weather.