Project Update, June 7

Concrete placement was completed in the middle section of the south cap to the expansion joints. The remaining sections of the south cap will be placed Friday. The sheet pile and backfill of the North side have been installed. The new 4x12 cap members were also installed on both sides the bridge. All work appeared to be in accordance with the plans or applicable engineer-approved field modifications.

Share Project Update, June 7 on Facebook Share Project Update, June 7 on Twitter Share Project Update, June 7 on Linkedin Email Project Update, June 7 link