Project Update, May 24

The installation of sheet pile at the South Abutment has been completed. The South Abutment has also been backfilled. Contractor started demo of the North Abutment and is installing sheet pile for the North Abutment. No work will be conducted on May 27th in observance of Memorial Day. Concrete crews will begin tying rebar cages on May 28th. The first concrete placement has been scheduled for the first week of June.