January 2026 Sidewalk Construction Update

Alljoy Community,

I want to start by apologizing for not sharing additional updates sooner. I know many of you have been watching this project closely, and I appreciate your patience.

Here’s where things stand today. Tree and vegetation clearing is complete, and the contractor has finished portions of the sidewalk on the south end of the project. Crews are now in the process of installing a new water main along Alljoy Road, between the north end of Confederate Avenue and Kirk Bluff Road. This work is necessary to allow for the installation of new storm drain pipes and inlets in that area.

Once the water main relocation is complete, storm drainage will be installed, followed by continued sidewalk construction.

At this time, the project is anticipated to be completed in late spring. I’ll continue to share updates as work progresses. Thank you for your continued patience and understanding.

Matt Krause