Notes from the 9.22.2026 Alljoy Community Meeting

  • Carolyn Smith presented on the status of the All Joy Preservation Commission (AJPC) community group.


  • Alljoy Zoning - Juliana Zadik, Deputy Director of Planning and Zoning presented on the current zoning protections for Alljoy, including the minimum lot sizes, setbacks, lot coverage percentage limits, and the minimum amount of private open space that is required for the two zones that cover the Alljoy neighborhood: T3 Edge and T3 Hamlet Neighborhood. Please see the images below for more information on those two zones.
  • River Buffer setbacks for single-family homes are 50 feet in T3 Edge and 35 feet in T3 Hamlet Neighborhood. The Community Development Code is available online here: https://library.municode.com/sc/beaufort_county/codes/community_development_code


  • Alljoy Go2Sewer - Jennifer Ray with BJWSA discussed the status of Phase 1 of the Go2Sewer project in Alljoy and she mentioned that planning is in the works for Phases 2 and 3, including an appropriation in this year's state budget for over $2 Million. They will post additional information on their website as updates occur. Once Phases 2 and 3 get closer, they will host sign-up meetings as they did previously with Phase 1. The website for the Alljoy Go2Sewer Project is: https://bjwsa.org/296/Alljoy


  • Bailey Memorial Park - Matt Krause and Assistant County Administrator Dylan Kidd provided an update on the park, which is now in the construction bidding phase. County staff hope to bring the selected bid to the Public Facilities Committee in October, and then it will go before full County Council. Click this link to down the conceptual master plan for the park: 03_Bailey Memorial Park Illustration.pdf


  • Stormwater Drainage Study - Taylor Brewer, Stormwater Program Manager, presented on the projects that were identified by the drainage study. $7 million has been allocated for Alljoy in the current year's Stormwater budget, which will help fund the top two projects. Additional funding will be pursued via grants and future fiscal years to complete the $20 million in identified projects. The drainage study report is still being finalized and once it is complete it can be shared with interested residents.


  • Sidewalk Construction - Jared Fralix, Assistant County Administrator, briefed the attendees on the current status of the sidewalk construction. The County is currently working through the legal process with the construction contract.


  • Boat Landing Design - Mark Johnson, Marine & Special Projects Manager at Beaufort County Engineering and Zack Hutcherson, Staff Civil Engineer at Davis & Floyd, presented on the conceptual design for the Alljoy boat landing. Jared Fralix led the meeting attendees through expressing their feedback on the design. Requests from the audience included: wanting to move the planned restrooms closer to the landing, and to see the car parking closest to the landing replaced with nothing but golf cart parking.