Updates from the June 5th, 2025 Public Meeting
The following projects were discussed at the June 5th public meeting:
BJWSA Sewer Project - representatives from BJWSA spoke about the first phase of the project moving forward in the near future, and that there are enough funds available that the homes included in that first phase will have their connection fees covered. Additional phases will be built as funds become available.
2 Mullet Street Demolition Project - the county is in the process of using grant funds to pay for the demolition.
Sidewalk Project - The bidding for the construction of the sidewalk completed on 6.6.25. It will take time to review the bids and award the winning bid.
Boat Landing Upgrades: Beaufort County Engineering is currently reviewing the RFQs (Request for Qualifications) submitted by companies that are necessary to decide on a design/construction management contractor. Once preliminary designs are available, another public meeting will be held with residents to discuss their opinions on the designs.
Drainage Study - The Rural Infrastructure Authority continues to review the county's contract for the project. Once approved, final award of the contract can be made to the contractor.