Phase I Update and Photo Highlights - March 2025

KEY WORK ITEMS ACCOMPLISHED

  • Roof installation 80% complete
  • Exterior wall Framing 100% complete
  • Exterior sheathing and liquid applied vapor barrier 100% complete
  • Interior framing 90% complete, Sheetrock installation started
  • Interior water/HVAC/electrical/ Fire suppression 80% complete
  • New domestic water and wastewater pipe installation 100% complete
  • New Temporary canopy and sidewalks at existing terminal 100% complete
  • Window frames and glass installed
  • Exterior EFIS is underway and approximately 60% complete
  • Interior Painting of exposed steel trusses is 100% complete

IMPORTANT COORDINATING ITEMS

  • Continue re-routing passengers through construction zones
  • Approve interior graphics, light fixtures and accessories
  • Begin parking lot study and prep gate locations
  • Next big step will be to complete sheetrock installation

NEAR-TERM LOOK-AHEAD

  • Pave two new arrival/departure lanes when canopy is complete
  • Continue roof panel installation
  • Wall insulation and interior sheetrock
  • Continue interior wiring and utility work
  • Complete temporary canopy sidewalks