Phase I Update and Photo Highlights - March 2025
KEY WORK ITEMS ACCOMPLISHED
- Roof installation 80% complete
- Exterior wall Framing 100% complete
- Exterior sheathing and liquid applied vapor barrier 100% complete
- Interior framing 90% complete, Sheetrock installation started
- Interior water/HVAC/electrical/ Fire suppression 80% complete
- New domestic water and wastewater pipe installation 100% complete
- New Temporary canopy and sidewalks at existing terminal 100% complete
- Window frames and glass installed
- Exterior EFIS is underway and approximately 60% complete
- Interior Painting of exposed steel trusses is 100% complete
IMPORTANT COORDINATING ITEMS
- Continue re-routing passengers through construction zones
- Approve interior graphics, light fixtures and accessories
- Begin parking lot study and prep gate locations
- Next big step will be to complete sheetrock installation
NEAR-TERM LOOK-AHEAD
- Pave two new arrival/departure lanes when canopy is complete
- Continue roof panel installation
- Wall insulation and interior sheetrock
- Continue interior wiring and utility work
- Complete temporary canopy sidewalks
Share Phase I Update and Photo Highlights - March 2025 on Facebook
Share Phase I Update and Photo Highlights - March 2025 on Twitter
Share Phase I Update and Photo Highlights - March 2025 on Linkedin
Email Phase I Update and Photo Highlights - March 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends