Share Mid-month Photo Highlights - September 15, 2025 on Facebook
Share Mid-month Photo Highlights - September 15, 2025 on Linkedin
Email Mid-month Photo Highlights - September 15, 2025 link
Share End of Month Photo Highlights - August 30, 2025 on Facebook
Share End of Month Photo Highlights - August 30, 2025 on Linkedin
Email End of Month Photo Highlights - August 30, 2025 link
Share Mid-month Photo Highlights - Aug 15, 2025 on Facebook
Share Mid-month Photo Highlights - Aug 15, 2025 on Linkedin
Email Mid-month Photo Highlights - Aug 15, 2025 link
Share End-of-Month Photo Highlights - July 31, 2025 on Facebook
Share End-of-Month Photo Highlights - July 31, 2025 on Linkedin
Email End-of-Month Photo Highlights - July 31, 2025 link
Share Mid-month Photo Highlights - July 15, 2025 on Facebook
Share Mid-month Photo Highlights - July 15, 2025 on Linkedin
Email Mid-month Photo Highlights - July 15, 2025 link
Share End-of-Month Photo Highlights - June 30,205 on Facebook
Share End-of-Month Photo Highlights - June 30,205 on Linkedin
Email End-of-Month Photo Highlights - June 30,205 link
Share End-of-Month Photo Highlights - May 30, 2025 on Facebook
Share End-of-Month Photo Highlights - May 30, 2025 on Linkedin
Email End-of-Month Photo Highlights - May 30, 2025 link
Share Mid-Month Photo Highlights - May 15, 2025 on Facebook
Share Mid-Month Photo Highlights - May 15, 2025 on Linkedin
Email Mid-Month Photo Highlights - May 15, 2025 link
Share End-of-Month Update and Photo Highlights - April 30, 2025 on Facebook
Share End-of-Month Update and Photo Highlights - April 30, 2025 on Linkedin
Email End-of-Month Update and Photo Highlights - April 30, 2025 link
KEY WORK ITEMS ACCOMPLISHED
- Roof installation 90% complete
- Sheetrock installation 40% complete
- Exterior doors installed
- Interior water/HVAC/electrical/ Fire suppression 90% complete
- Window frames and glass installed.
- Exterior EFIS is complete
IMPORTANT COORDINATING ITEMS
- Continue safely routing passengers through construction zones
- Approve interior graphics, light fixtures and accessories
- Next big step will be to complete sheet rock installation
- Pave final arrival lanes for a total of four lanes
NEAR-TERM LOOK AHEAD
- Terazzo floor test installation
- Wall insulation and interior sheet rock
-
End of May – all lanes will open for summer vehicular traffic



Share Mid-Month Photo Highlights - April 15, 2025 on Facebook
Share Mid-Month Photo Highlights - April 15, 2025 on Linkedin
Email Mid-Month Photo Highlights - April 15, 2025 link