End-of-Month Update and Photo Highlights - April 30, 2025
KEY WORK ITEMS ACCOMPLISHED
- Roof installation 90% complete
- Sheetrock installation 40% complete
- Exterior doors installed
- Interior water/HVAC/electrical/ Fire suppression 90% complete
- Window frames and glass installed.
- Exterior EFIS is complete
IMPORTANT COORDINATING ITEMS
- Continue safely routing passengers through construction zones
- Approve interior graphics, light fixtures and accessories
- Next big step will be to complete sheet rock installation
- Pave final arrival lanes for a total of four lanes
NEAR-TERM LOOK AHEAD
- Terazzo floor test installation
- Wall insulation and interior sheet rock
-
End of May – all lanes will open for summer vehicular traffic
Share End-of-Month Update and Photo Highlights - April 30, 2025 on Facebook
Share End-of-Month Update and Photo Highlights - April 30, 2025 on Twitter
Share End-of-Month Update and Photo Highlights - April 30, 2025 on Linkedin
Email End-of-Month Update and Photo Highlights - April 30, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends