End-of-Month Update and Photo Highlights - April 30, 2025

KEY WORK ITEMS ACCOMPLISHED

  • Roof installation 90% complete
  • Sheetrock installation 40% complete
  • Exterior doors installed
  • Interior water/HVAC/electrical/ Fire suppression 90% complete
  • Window frames and glass installed.
  • Exterior EFIS is complete

IMPORTANT COORDINATING ITEMS

  • Continue safely routing passengers through construction zones
  • Approve interior graphics, light fixtures and accessories
  • Next big step will be to complete sheet rock installation
  • Pave final arrival lanes for a total of four lanes

NEAR-TERM LOOK AHEAD

  • Terazzo floor test installation
  • Wall insulation and interior sheet rock
  • End of May – all lanes will open for summer vehicular traffic