Phase I Update - September 2024
Key Work Items Accomplished
- New terminal vehicle lane curbing installed.
- Pedestrian sidewalk placed and ready for concrete.
- New arrival/departure lanes graded and prepped for asphalt.
- EV charging stations (x2) site work complete.
- Steel structure for new TSA screening checkpoint area and exit lane 80% complete.
- Bioretention stormwater facility work 50% complete.
Important Coordinating Items
- Continue re-routing passengers through construction zones
- Demo remaining traffic lane and pave
- Approve interior graphics, light fixtures and accessories.
- Begin parking lot study and prep gate locations.
- Next big step will be framers inside new building.
Near-Term Look-Ahead
- PAVE 2 NEW ARRIVAL/DEPARTURE LANES
- POUR PEDESTRIAN SIDEWALK AND MAIN ENTRY WALKWAY
- COMPLETE SECTION 1 STEEL AND BEGIN SECTION 2
- INSTALL ROOF DECKING AND ROOF PANELS
- POUR FINAL SLAB ZONE 2
PROGRESS PHOTOS
Share Phase I Update - September 2024 on Facebook
Share Phase I Update - September 2024 on Twitter
Share Phase I Update - September 2024 on Linkedin
Email Phase I Update - September 2024 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends