Phase I Update - September 2024

Key Work Items Accomplished

  • New terminal vehicle lane curbing installed.
  • Pedestrian sidewalk placed and ready for concrete.
  • New arrival/departure lanes graded and prepped for asphalt.
  • EV charging stations (x2) site work complete.
  • Steel structure for new TSA screening checkpoint area and exit lane 80% complete.
  • Bioretention stormwater facility work 50% complete.

Important Coordinating Items

  • Continue re-routing passengers through construction zones
  • Demo remaining traffic lane and pave
  • Approve interior graphics, light fixtures and accessories.
  • Begin parking lot study and prep gate locations.
  • Next big step will be framers inside new building.

Near-Term Look-Ahead

  • PAVE 2 NEW ARRIVAL/DEPARTURE LANES
  • POUR PEDESTRIAN SIDEWALK AND MAIN ENTRY WALKWAY
  • COMPLETE SECTION 1 STEEL AND BEGIN SECTION 2
  • INSTALL ROOF DECKING AND ROOF PANELS
  • POUR FINAL SLAB ZONE 2

PROGRESS PHOTOS


Share Phase I Update - September 2024 on Facebook Share Phase I Update - September 2024 on Twitter Share Phase I Update - September 2024 on Linkedin Email Phase I Update - September 2024 link