Phase I Update - December 2024

KEY WORK ITEMS ACCOMPLISHED

  • New terminal vehicle lane Storm Water drains completed.
  • Pedestrian sidewalk concrete complete.
  • Steel structure for new TSA screening checkpoint area and exit lane 90% complete.
  • Roof Decking 80% complete.
  • Awning footers poured and steel supports installed
  • Bioretention stormwater facility work 75% complete.
  • Interior metal stud installation 50% complete.

IMPORTANT COORDINATION ITEMS

  • Continue re-routing passengers through construction zones
  • Demo remaining traffic lane and pave
  • Approve interior graphics, light fixtures and accessories.
  • Begin parking lot study and prep gate locations.
  • Next big step will be framers inside new building.

NEAR-TERM LOOK-AHEAD

  • Pave 2 new arrival/departure lanes
  • Pour final concrete slab
  • Install roof panels
  • Complete metal studs and begin sheet rock
  • Interior wiring and utility work

WEEK IN PHOTOS | 01/04/25 - 01/10/25