Phase I Update - December 2024
KEY WORK ITEMS ACCOMPLISHED
- New terminal vehicle lane Storm Water drains completed.
- Pedestrian sidewalk concrete complete.
- Steel structure for new TSA screening checkpoint area and exit lane 90% complete.
- Roof Decking 80% complete.
- Awning footers poured and steel supports installed
- Bioretention stormwater facility work 75% complete.
- Interior metal stud installation 50% complete.
IMPORTANT COORDINATION ITEMS
- Continue re-routing passengers through construction zones
- Demo remaining traffic lane and pave
- Approve interior graphics, light fixtures and accessories.
- Begin parking lot study and prep gate locations.
- Next big step will be framers inside new building.
NEAR-TERM LOOK-AHEAD
- Pave 2 new arrival/departure lanes
- Pour final concrete slab
- Install roof panels
- Complete metal studs and begin sheet rock
- Interior wiring and utility work
WEEK IN PHOTOS | 01/04/25 - 01/10/25
Share Phase I Update - December 2024 on Facebook
Share Phase I Update - December 2024 on Twitter
Share Phase I Update - December 2024 on Linkedin
Email Phase I Update - December 2024 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends