Phase I Update - January and February 2025
KEY WORK ITEMS ACCOMPLISHED
- Roof insulation 50% complete
- Roof panel installation 70% complete
- Temporary canopy decking 100% complete
- Interior framing 80% complete
- Interior water/HVAC/electrical 50% complete
- Civil work, water, and wastewater pipe installation 40% complete
- Purple exterior sheet rock 100% complete
- Black sealant around exterior 75% complete
IMPORTANT COORDINATING ITEMS
- Continue re-routing passengers through construction zones
- Approve interior graphics, light fixtures and accessories
- Begin parking lot study and prep gate locations
- Next big step will sheet rock installation on the interior
NEAR-TERM LOOK-AHEAD
- Pave 2 new arrival/departure lanes when canopy is complete
- Continue roof panels installation
- Interior sheet rock
- Continue interior wiring and utility work
- Complete temporary canopy
- Begin interior doors and window frame in
Share Phase I Update - January and February 2025 on Facebook
Share Phase I Update - January and February 2025 on Twitter
Share Phase I Update - January and February 2025 on Linkedin
Email Phase I Update - January and February 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends