Phase I Update - January and February 2025

KEY WORK ITEMS ACCOMPLISHED

  • Roof insulation 50% complete
  • Roof panel installation 70% complete
  • Temporary canopy decking 100% complete
  • Interior framing 80% complete
  • Interior water/HVAC/electrical 50% complete
  • Civil work, water, and wastewater pipe installation 40% complete
  • Purple exterior sheet rock 100% complete
  • Black sealant around exterior 75% complete

IMPORTANT COORDINATING ITEMS

  • Continue re-routing passengers through construction zones
  • Approve interior graphics, light fixtures and accessories
  • Begin parking lot study and prep gate locations
  • Next big step will sheet rock installation on the interior

NEAR-TERM LOOK-AHEAD

  • Pave 2 new arrival/departure lanes when canopy is complete
  • Continue roof panels installation
  • Interior sheet rock
  • Continue interior wiring and utility work
  • Complete temporary canopy
  • Begin interior doors and window frame in