Phase I Update - November 2024
Key Work Items Accomplished
- Arrival and Departures lanes 1 & 2 installed and open.
- Entrance walkways completed.
- Steel structure for new TSA screening checkpoint area, exit lane, & boarding gate area 95% complete.
- Mezzanine level concrete complete.
- Generator and Switch installed.
- Old Arrival lanes removed.
- Entrance Canopy land prep complete.
Important Coordination Items
- Continue re-routing passengers through construction zones.
- Coordinate with tenants, traffic control
- Approve bathroom fixtures
- Begin parking lot study and prep gate locations.
- Next major item is roof installation.
Near-Term Look-Ahead
- POUR FOOTERS FOR ENTRANCE CANOPY
- COMPLETE STEEL INSTALL
- INSTALL REMAINING SLAB
- INSTALL ROOF DECKING AND ROOF PANELS
- INTERIOR WALL FRAMING
- HVAC LAYOUT
WEEK IN PHOTOS | 11/30/24 - 12/06/24
Share Phase I Update - November 2024 on Facebook
Share Phase I Update - November 2024 on Twitter
Share Phase I Update - November 2024 on Linkedin
Email Phase I Update - November 2024 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends