Phase I Update - November 2024

Key Work Items Accomplished

  • Arrival and Departures lanes 1 & 2 installed and open.
  • Entrance walkways completed.
  • Steel structure for new TSA screening checkpoint area, exit lane, & boarding gate area 95% complete.
  • Mezzanine level concrete complete.
  • Generator and Switch installed.
  • Old Arrival lanes removed.
  • Entrance Canopy land prep complete.

Important Coordination Items

  • Continue re-routing passengers through construction zones.
  • Coordinate with tenants, traffic control
  • Approve bathroom fixtures
  • Begin parking lot study and prep gate locations.
  • Next major item is roof installation.

Near-Term Look-Ahead

  • POUR FOOTERS FOR ENTRANCE CANOPY
  • COMPLETE STEEL INSTALL
  • INSTALL REMAINING SLAB
  • INSTALL ROOF DECKING AND ROOF PANELS
  • INTERIOR WALL FRAMING
  • HVAC LAYOUT

WEEK IN PHOTOS | 11/30/24 - 12/06/24