Phase I Update - July 2024

Key Work Items Accomplished

  • Arrival and Departure lanes have been re-routed. Down to single lane.
  • First 2 rows of parking spaces have been cleared and removed.
  • All underground facilities have been installed, connecting the current facilities to the new terminal.
  • 90% of the designed steel on site.
  • Previously installed “dry” pond correction complete.
  • Concrete colors/texture and window tinting approved.

Important Coordinating Items

  • Arrange parking lot after lane paving to include handicap and new rental car locations.
  • Traffic Control and night work monitoring.
  • Approve interior graphics, light fixtures and accessories.
  • Begin parking lot study and prep gate locations.

Near-Term Look-Ahead

  • Complete arrival and departure lane facility work
  • Pave new arrival/departure lanes
  • Steel construction (going vertical)
  • Pour final slab zone 2

PROGRESS PHOTOS

Underground Facilities Work

Dry Pond Correction



Arrival/Departure Traffic Lane Work

Final Footer Installation

Parking Space Demo