Phase I Update - July 2024
Key Work Items Accomplished
- Arrival and Departure lanes have been re-routed. Down to single lane.
- First 2 rows of parking spaces have been cleared and removed.
- All underground facilities have been installed, connecting the current facilities to the new terminal.
- 90% of the designed steel on site.
- Previously installed “dry” pond correction complete.
- Concrete colors/texture and window tinting approved.
Important Coordinating Items
- Arrange parking lot after lane paving to include handicap and new rental car locations.
- Traffic Control and night work monitoring.
- Approve interior graphics, light fixtures and accessories.
- Begin parking lot study and prep gate locations.
Near-Term Look-Ahead
- Complete arrival and departure lane facility work
- Pave new arrival/departure lanes
- Steel construction (going vertical)
- Pour final slab zone 2
PROGRESS PHOTOS
Underground Facilities Work
Dry Pond Correction
Arrival/Departure Traffic Lane Work
Final Footer Installation
Parking Space Demo
Share Phase I Update - July 2024 on Facebook
Share Phase I Update - July 2024 on Twitter
Share Phase I Update - July 2024 on Linkedin
Email Phase I Update - July 2024 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends