Phase I Update - June 2024
Key Work Items Accomplished (April 22nd-June 6th)
- Surface wall installed and grouted
- Slab poured and cured (lower)
- Slab prep and grading complete (upper)
- Arrival/Departure lanes palm trees and shrubs removed
- Curbing for new entrance lane complete
- Underground facilities under entrance lane removed and reconfigured
- Stormwater piping
Important Coordination Items
- Coordination with terminal tenants & customers for parking disturbances
- Parking and traffic flow impact for 2 to 4 months
- Website, social media updates
- Traffic Control and night work monitoring
- Summer season push – Airport Ambassadors on duty