Phase I Update - June 2024

Key Work Items Accomplished (April 22nd-June 6th)
  • Surface wall installed and grouted
  • Slab poured and cured (lower)
  • Slab prep and grading complete (upper)
  • Arrival/Departure lanes palm trees and shrubs removed
  • Curbing for new entrance lane complete
  • Underground facilities under entrance lane removed and reconfigured
    • Stormwater piping
Important Coordination Items
  • Coordination with terminal tenants & customers for parking disturbances
    • Parking and traffic flow impact for 2 to 4 months
    • Website, social media updates
  • Traffic Control and night work monitoring

  • Summer season push – Airport Ambassadors on duty