Phase I Update - October 2024
Key Work Items Accomplished
- New terminal vehicle lane curbing installed.
- Parking lot side pedestrian sidewalk installed.
- Outer new arrival/departure lanes graded and prepped for asphalt.
- EV charging stations (x2) site work complete.
- Steel structure for new TSA screening checkpoint area, exit lane, & boarding gate area 80% complete.
- Bioretention stormwater facility work 50% complete.
- Water main line tie-in complete.
- New dumpster pad installed.
Important Coordinating Items
- Continue re-routing passengers through construction zones.
- Demo remaining traffic lane and pave.
- Approve interior graphics, light fixtures and accessories.
- Begin parking lot study and prep gate locations.
- Next big step will be framers inside new building.
Near-Term Look-Ahead
- REMOVE TEMP ARRIVAL/DEPARTURE LANES
- COMPLETE STEEL INSTALL
- INSTALL REMAINING SLAB
- INSTALL ROOF DECKING AND ROOF PANELS
- WORK BEGINNING ON CENTER ENTRANCE FOR CANOPY
Week in Photos | 10/26 - 11/01
Share Phase I Update - October 2024 on Facebook
Share Phase I Update - October 2024 on Twitter
Share Phase I Update - October 2024 on Linkedin
Email Phase I Update - October 2024 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends