Phase I Update - October 2024

Key Work Items Accomplished

  • New terminal vehicle lane curbing installed.
  • Parking lot side pedestrian sidewalk installed.
  • Outer new arrival/departure lanes graded and prepped for asphalt.
  • EV charging stations (x2) site work complete.
  • Steel structure for new TSA screening checkpoint area, exit lane, & boarding gate area 80% complete.
  • Bioretention stormwater facility work 50% complete.
  • Water main line tie-in complete.
  • New dumpster pad installed.


Important Coordinating Items

  • Continue re-routing passengers through construction zones.
  • Demo remaining traffic lane and pave.
  • Approve interior graphics, light fixtures and accessories.
  • Begin parking lot study and prep gate locations.
  • Next big step will be framers inside new building.


Near-Term Look-Ahead

  • REMOVE TEMP ARRIVAL/DEPARTURE LANES
  • COMPLETE STEEL INSTALL
  • INSTALL REMAINING SLAB
  • INSTALL ROOF DECKING AND ROOF PANELS
  • WORK BEGINNING ON CENTER ENTRANCE FOR CANOPY

Week in Photos | 10/26 - 11/01




Share Phase I Update - October 2024 on Facebook Share Phase I Update - October 2024 on Twitter Share Phase I Update - October 2024 on Linkedin Email Phase I Update - October 2024 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>