Share Week in Photos | Dec 7 - Dec 13 on Facebook
Share Week in Photos | Dec 7 - Dec 13 on Linkedin
Email Week in Photos | Dec 7 - Dec 13 link
Share Phase I Update - November 2024 on Facebook
Share Phase I Update - November 2024 on Linkedin
Email Phase I Update - November 2024 link
Key Work Items Accomplished
- Arrival and Departures lanes 1 & 2 installed and open.
- Entrance walkways completed.
- Steel structure for new TSA screening checkpoint area, exit lane, & boarding gate area 95% complete.
- Mezzanine level concrete complete.
- Generator and Switch installed.
- Old Arrival lanes removed.
- Entrance Canopy land prep complete.
Important Coordination Items
- Continue re-routing passengers through construction zones.
- Coordinate with tenants, traffic control
- Approve bathroom fixtures
- Begin parking lot study and prep gate locations.
- Next major item is roof installation.
Near-Term Look-Ahead
- POUR FOOTERS FOR ENTRANCE CANOPY
- COMPLETE STEEL INSTALL
- INSTALL REMAINING SLAB
- INSTALL ROOF DECKING AND ROOF PANELS
- INTERIOR WALL FRAMING
- HVAC LAYOUT
WEEK IN PHOTOS | 11/30/24 - 12/06/24



Share Week in Photos | Nov 23 - Nov 29 on Facebook
Share Week in Photos | Nov 23 - Nov 29 on Linkedin
Email Week in Photos | Nov 23 - Nov 29 link
Share Week in Photos | Nov 16 - Nov 22 on Facebook
Share Week in Photos | Nov 16 - Nov 22 on Linkedin
Email Week in Photos | Nov 16 - Nov 22 link
Share Week in Photos | 11/09 - 11/15 on Facebook
Share Week in Photos | 11/09 - 11/15 on Linkedin
Email Week in Photos | 11/09 - 11/15 link
Share Week in Photos | 11/02 - 11/08 on Facebook
Share Week in Photos | 11/02 - 11/08 on Linkedin
Email Week in Photos | 11/02 - 11/08 link
Share Phase I Update - October 2024 on Facebook
Share Phase I Update - October 2024 on Linkedin
Email Phase I Update - October 2024 link
Key Work Items Accomplished
- New terminal vehicle lane curbing installed.
- Parking lot side pedestrian sidewalk installed.
- Outer new arrival/departure lanes graded and prepped for asphalt.
- EV charging stations (x2) site work complete.
- Steel structure for new TSA screening checkpoint area, exit lane, & boarding gate area 80% complete.
- Bioretention stormwater facility work 50% complete.
- Water main line tie-in complete.
- New dumpster pad installed.
Important Coordinating Items
- Continue re-routing passengers through construction zones.
- Demo remaining traffic lane and pave.
- Approve interior graphics, light fixtures and accessories.
- Begin parking lot study and prep gate locations.
- Next big step will be framers inside new building.
Near-Term Look-Ahead
- REMOVE TEMP ARRIVAL/DEPARTURE LANES
- COMPLETE STEEL INSTALL
- INSTALL REMAINING SLAB
- INSTALL ROOF DECKING AND ROOF PANELS
- WORK BEGINNING ON CENTER ENTRANCE FOR CANOPY
Week in Photos | 10/26 - 11/01


Share Week in Photos | Oct 19-25 on Facebook
Share Week in Photos | Oct 19-25 on Linkedin
Email Week in Photos | Oct 19-25 link
Share Week in Photos | Oct 11-18 on Facebook
Share Week in Photos | Oct 11-18 on Linkedin
Email Week in Photos | Oct 11-18 link
Share Phase I Update - September 2024 on Facebook
Share Phase I Update - September 2024 on Linkedin
Email Phase I Update - September 2024 link
Key Work Items Accomplished
- New terminal vehicle lane curbing installed.
- Pedestrian sidewalk placed and ready for concrete.
- New arrival/departure lanes graded and prepped for asphalt.
- EV charging stations (x2) site work complete.
- Steel structure for new TSA screening checkpoint area and exit lane 80% complete.
- Bioretention stormwater facility work 50% complete.
Important Coordinating Items
- Continue re-routing passengers through construction zones
- Demo remaining traffic lane and pave
- Approve interior graphics, light fixtures and accessories.
- Begin parking lot study and prep gate locations.
- Next big step will be framers inside new building.
Near-Term Look-Ahead
- PAVE 2 NEW ARRIVAL/DEPARTURE LANES
- POUR PEDESTRIAN SIDEWALK AND MAIN ENTRY WALKWAY
- COMPLETE SECTION 1 STEEL AND BEGIN SECTION 2
- INSTALL ROOF DECKING AND ROOF PANELS
- POUR FINAL SLAB ZONE 2
PROGRESS PHOTOS
