Hilton Head Island Airport Terminal Improvements

Share Hilton Head Island Airport Terminal Improvements on Facebook Share Hilton Head Island Airport Terminal Improvements on Twitter Share Hilton Head Island Airport Terminal Improvements on Linkedin Email Hilton Head Island Airport Terminal Improvements link

Hilton Head Island Airport is thrilled to announce the commencement of Phase I of its Terminal Improvements Project, aimed at modernizing and enhancing the airport's facilities to meet the growing needs of passengers and the surrounding community. The project is spearheaded by the architecture firm The Wilson Group, headquartered in Charlotte, NC, and will be executed by Edison Foard. The contract, valued at $30,898,447.83, is projected to span two years and is funded through a combination of FAA Grants, SC Aeronautics Grants, State Funds secured by the local delegation and airport revenue.

For more information about the Hilton Head Island Airport, visit www.hiltonheadairport.com. For more information on this and other exciting Beaufort County projects, please visit www.beaufortcountysc.gov.

Hilton Head Island Airport is thrilled to announce the commencement of Phase I of its Terminal Improvements Project, aimed at modernizing and enhancing the airport's facilities to meet the growing needs of passengers and the surrounding community. The project is spearheaded by the architecture firm The Wilson Group, headquartered in Charlotte, NC, and will be executed by Edison Foard. The contract, valued at $30,898,447.83, is projected to span two years and is funded through a combination of FAA Grants, SC Aeronautics Grants, State Funds secured by the local delegation and airport revenue.

For more information about the Hilton Head Island Airport, visit www.hiltonheadairport.com. For more information on this and other exciting Beaufort County projects, please visit www.beaufortcountysc.gov.

  • Week in Photos | Dec 7 - Dec 13

    Share Week in Photos | Dec 7 - Dec 13 on Facebook Share Week in Photos | Dec 7 - Dec 13 on Twitter Share Week in Photos | Dec 7 - Dec 13 on Linkedin Email Week in Photos | Dec 7 - Dec 13 link

  • Phase I Update - November 2024

    Share Phase I Update - November 2024 on Facebook Share Phase I Update - November 2024 on Twitter Share Phase I Update - November 2024 on Linkedin Email Phase I Update - November 2024 link

    Key Work Items Accomplished

    • Arrival and Departures lanes 1 & 2 installed and open.
    • Entrance walkways completed.
    • Steel structure for new TSA screening checkpoint area, exit lane, & boarding gate area 95% complete.
    • Mezzanine level concrete complete.
    • Generator and Switch installed.
    • Old Arrival lanes removed.
    • Entrance Canopy land prep complete.

    Important Coordination Items

    • Continue re-routing passengers through construction zones.
    • Coordinate with tenants, traffic control
    • Approve bathroom fixtures
    • Begin parking lot study and prep gate locations.
    • Next major item is roof installation.

    Near-Term Look-Ahead

    • POUR FOOTERS FOR ENTRANCE CANOPY
    • COMPLETE STEEL INSTALL
    • INSTALL REMAINING SLAB
    • INSTALL ROOF DECKING AND ROOF PANELS
    • INTERIOR WALL FRAMING
    • HVAC LAYOUT

    WEEK IN PHOTOS | 11/30/24 - 12/06/24



  • Week in Photos | Nov 23 - Nov 29

    Share Week in Photos | Nov 23 - Nov 29 on Facebook Share Week in Photos | Nov 23 - Nov 29 on Twitter Share Week in Photos | Nov 23 - Nov 29 on Linkedin Email Week in Photos | Nov 23 - Nov 29 link

  • Week in Photos | Nov 16 - Nov 22

    Share Week in Photos | Nov 16 - Nov 22 on Facebook Share Week in Photos | Nov 16 - Nov 22 on Twitter Share Week in Photos | Nov 16 - Nov 22 on Linkedin Email Week in Photos | Nov 16 - Nov 22 link

  • Week in Photos | 11/09 - 11/15

    Share Week in Photos | 11/09 - 11/15 on Facebook Share Week in Photos | 11/09 - 11/15 on Twitter Share Week in Photos | 11/09 - 11/15 on Linkedin Email Week in Photos | 11/09 - 11/15 link

  • Week in Photos | 11/02 - 11/08

    Share Week in Photos | 11/02 - 11/08 on Facebook Share Week in Photos | 11/02 - 11/08 on Twitter Share Week in Photos | 11/02 - 11/08 on Linkedin Email Week in Photos | 11/02 - 11/08 link

  • Phase I Update - October 2024

    Share Phase I Update - October 2024 on Facebook Share Phase I Update - October 2024 on Twitter Share Phase I Update - October 2024 on Linkedin Email Phase I Update - October 2024 link

    Key Work Items Accomplished

    • New terminal vehicle lane curbing installed.
    • Parking lot side pedestrian sidewalk installed.
    • Outer new arrival/departure lanes graded and prepped for asphalt.
    • EV charging stations (x2) site work complete.
    • Steel structure for new TSA screening checkpoint area, exit lane, & boarding gate area 80% complete.
    • Bioretention stormwater facility work 50% complete.
    • Water main line tie-in complete.
    • New dumpster pad installed.

    Important Coordinating Items

    • Continue re-routing passengers through construction zones.
    • Demo remaining traffic lane and pave.
    • Approve interior graphics, light fixtures and accessories.
    • Begin parking lot study and prep gate locations.
    • Next big step will be framers inside new building.

    Near-Term Look-Ahead

    • REMOVE TEMP ARRIVAL/DEPARTURE LANES
    • COMPLETE STEEL INSTALL
    • INSTALL REMAINING SLAB
    • INSTALL ROOF DECKING AND ROOF PANELS
    • WORK BEGINNING ON CENTER ENTRANCE FOR CANOPY

    Week in Photos | 10/26 - 11/01




  • Week in Photos | Oct 19-25

    Share Week in Photos | Oct 19-25 on Facebook Share Week in Photos | Oct 19-25 on Twitter Share Week in Photos | Oct 19-25 on Linkedin Email Week in Photos | Oct 19-25 link

  • Week in Photos | Oct 11-18

    Share Week in Photos | Oct 11-18 on Facebook Share Week in Photos | Oct 11-18 on Twitter Share Week in Photos | Oct 11-18 on Linkedin Email Week in Photos | Oct 11-18 link

  • Phase I Update - September 2024

    Share Phase I Update - September 2024 on Facebook Share Phase I Update - September 2024 on Twitter Share Phase I Update - September 2024 on Linkedin Email Phase I Update - September 2024 link

    Key Work Items Accomplished

    • New terminal vehicle lane curbing installed.
    • Pedestrian sidewalk placed and ready for concrete.
    • New arrival/departure lanes graded and prepped for asphalt.
    • EV charging stations (x2) site work complete.
    • Steel structure for new TSA screening checkpoint area and exit lane 80% complete.
    • Bioretention stormwater facility work 50% complete.

    Important Coordinating Items

    • Continue re-routing passengers through construction zones
    • Demo remaining traffic lane and pave
    • Approve interior graphics, light fixtures and accessories.
    • Begin parking lot study and prep gate locations.
    • Next big step will be framers inside new building.

    Near-Term Look-Ahead

    • PAVE 2 NEW ARRIVAL/DEPARTURE LANES
    • POUR PEDESTRIAN SIDEWALK AND MAIN ENTRY WALKWAY
    • COMPLETE SECTION 1 STEEL AND BEGIN SECTION 2
    • INSTALL ROOF DECKING AND ROOF PANELS
    • POUR FINAL SLAB ZONE 2

    PROGRESS PHOTOS