KEY WORK ITEMS ACCOMPLISHED
- New terminal vehicle lane Storm Water drains completed.
- Pedestrian sidewalk concrete complete.
- Steel structure for new TSA screening checkpoint area and exit lane 90% complete.
- Roof Decking 80% complete.
- Awning footers poured and steel supports installed
- Bioretention stormwater facility work 75% complete.
- Interior metal stud installation 50% complete.
IMPORTANT COORDINATION ITEMS
- Continue re-routing passengers through construction zones
- Demo remaining traffic lane and pave
- Approve interior graphics, light fixtures and accessories.
- Begin parking lot study and prep gate locations.
- Next big step will be framers inside new building.
NEAR-TERM LOOK-AHEAD
- Pave 2 new arrival/departure lanes
- Pour final concrete slab
- Install roof panels
- Complete metal studs and begin sheet rock
- Interior wiring and utility work
WEEK IN PHOTOS | 01/04/25 - 01/10/25
Share Week in Photos | Dec 28 - Jan 03, 2025 on Facebook
Share Week in Photos | Dec 28 - Jan 03, 2025 on Linkedin
Email Week in Photos | Dec 28 - Jan 03, 2025 link
Share Week in Photos | Dec 21 - Dec 27 on Facebook
Share Week in Photos | Dec 21 - Dec 27 on Linkedin
Email Week in Photos | Dec 21 - Dec 27 link
Share Week in Photos | Dec 14 - Dec 20 on Facebook
Share Week in Photos | Dec 14 - Dec 20 on Linkedin
Email Week in Photos | Dec 14 - Dec 20 link
Share Week in Photos | Dec 7 - Dec 13 on Facebook
Share Week in Photos | Dec 7 - Dec 13 on Linkedin
Email Week in Photos | Dec 7 - Dec 13 link
Share Phase I Update - November 2024 on Facebook
Share Phase I Update - November 2024 on Linkedin
Email Phase I Update - November 2024 link
Key Work Items Accomplished
- Arrival and Departures lanes 1 & 2 installed and open.
- Entrance walkways completed.
- Steel structure for new TSA screening checkpoint area, exit lane, & boarding gate area 95% complete.
- Mezzanine level concrete complete.
- Generator and Switch installed.
- Old Arrival lanes removed.
- Entrance Canopy land prep complete.
Important Coordination Items
- Continue re-routing passengers through construction zones.
- Coordinate with tenants, traffic control
- Approve bathroom fixtures
- Begin parking lot study and prep gate locations.
- Next major item is roof installation.
Near-Term Look-Ahead
- POUR FOOTERS FOR ENTRANCE CANOPY
- COMPLETE STEEL INSTALL
- INSTALL REMAINING SLAB
- INSTALL ROOF DECKING AND ROOF PANELS
- INTERIOR WALL FRAMING
- HVAC LAYOUT
WEEK IN PHOTOS | 11/30/24 - 12/06/24
Share Week in Photos | Nov 23 - Nov 29 on Facebook
Share Week in Photos | Nov 23 - Nov 29 on Linkedin
Email Week in Photos | Nov 23 - Nov 29 link
Share Week in Photos | Nov 16 - Nov 22 on Facebook
Share Week in Photos | Nov 16 - Nov 22 on Linkedin
Email Week in Photos | Nov 16 - Nov 22 link
Share Week in Photos | 11/09 - 11/15 on Facebook
Share Week in Photos | 11/09 - 11/15 on Linkedin
Email Week in Photos | 11/09 - 11/15 link