Share Week in Photos | Dec 21 - Dec 27 on Facebook
Share Week in Photos | Dec 21 - Dec 27 on Linkedin
Email Week in Photos | Dec 21 - Dec 27 link
Share Week in Photos | Dec 14 - Dec 20 on Facebook
Share Week in Photos | Dec 14 - Dec 20 on Linkedin
Email Week in Photos | Dec 14 - Dec 20 link
Share Week in Photos | Dec 7 - Dec 13 on Facebook
Share Week in Photos | Dec 7 - Dec 13 on Linkedin
Email Week in Photos | Dec 7 - Dec 13 link
Share Phase I Update - November 2024 on Facebook
Share Phase I Update - November 2024 on Linkedin
Email Phase I Update - November 2024 link
Key Work Items Accomplished 
- Arrival and Departures lanes 1 & 2 installed and open.
 
- Entrance walkways completed.
 
- Steel structure for new TSA screening checkpoint area, exit lane, & boarding gate area 95% complete.
 
- Mezzanine level concrete complete.
 
- Generator and Switch installed.
 
- Old Arrival lanes removed.
 
- Entrance Canopy land prep complete.
 
 Important Coordination Items
- Continue re-routing passengers through construction zones.
 
- Coordinate with tenants, traffic control
 
- Approve bathroom fixtures
 
- Begin parking lot study and prep gate locations.
 
- Next major item is roof installation.
 
 Near-Term Look-Ahead
- POUR FOOTERS FOR ENTRANCE CANOPY
 
- COMPLETE STEEL INSTALL
 
- INSTALL REMAINING SLAB
 
- INSTALL ROOF DECKING AND ROOF PANELS
 
- INTERIOR WALL FRAMING
 
- HVAC LAYOUT
 
WEEK IN PHOTOS | 11/30/24 - 12/06/24



 
Share Week in Photos | Nov 23 - Nov 29 on Facebook
Share Week in Photos | Nov 23 - Nov 29 on Linkedin
Email Week in Photos | Nov 23 - Nov 29 link
Share Week in Photos | Nov 16 - Nov 22 on Facebook
Share Week in Photos | Nov 16 - Nov 22 on Linkedin
Email Week in Photos | Nov 16 - Nov 22 link
Share Week in Photos | 11/09 - 11/15 on Facebook
Share Week in Photos | 11/09 - 11/15 on Linkedin
Email Week in Photos | 11/09 - 11/15 link
Share Week in Photos | 11/02 - 11/08 on Facebook
Share Week in Photos | 11/02 - 11/08 on Linkedin
Email Week in Photos | 11/02 - 11/08 link
Share Phase I Update - October 2024 on Facebook
Share Phase I Update - October 2024 on Linkedin
Email Phase I Update - October 2024 link
Key Work Items Accomplished
- New terminal vehicle lane curbing installed.
 
- Parking lot side pedestrian sidewalk installed.
 
- Outer new arrival/departure lanes graded and prepped for asphalt.
 
- EV charging stations (x2) site work complete.
 
- Steel structure for new TSA screening checkpoint area, exit lane, & boarding gate area 80% complete.
 
- Bioretention stormwater facility work 50% complete.
 
- Water main line tie-in complete.
 
- New dumpster pad installed.
 
Important Coordinating Items
- Continue re-routing passengers through construction zones.
 
- Demo remaining traffic lane and pave.
 
- Approve interior graphics, light fixtures and accessories.
 
- Begin parking lot study and prep gate locations.
 
- Next big step will be framers inside new building.
 
Near-Term Look-Ahead
- REMOVE TEMP ARRIVAL/DEPARTURE LANES
 
- COMPLETE STEEL INSTALL
 
- INSTALL REMAINING SLAB
 
- INSTALL ROOF DECKING AND ROOF PANELS
 
- WORK BEGINNING ON CENTER ENTRANCE FOR CANOPY
 
Week in Photos | 10/26 - 11/01 


 
Share Week in Photos | Oct 19-25 on Facebook
Share Week in Photos | Oct 19-25 on Linkedin
Email Week in Photos | Oct 19-25 link