Key Work Items Accomplished
- New terminal vehicle lane curbing installed.
- Parking lot side pedestrian sidewalk installed.
- Outer new arrival/departure lanes graded and prepped for asphalt.
- EV charging stations (x2) site work complete.
- Steel structure for new TSA screening checkpoint area, exit lane, & boarding gate area 80% complete.
- Bioretention stormwater facility work 50% complete.
- Water main line tie-in complete.
- New dumpster pad installed.
Important Coordinating Items
- Continue re-routing passengers through construction zones.
- Demo remaining traffic lane and pave.
- Approve interior graphics, light fixtures and accessories.
- Begin parking lot study and prep gate locations.
- Next big step will be framers inside new building.
Near-Term Look-Ahead
- REMOVE TEMP ARRIVAL/DEPARTURE LANES
- COMPLETE STEEL INSTALL
- INSTALL REMAINING SLAB
- INSTALL ROOF DECKING AND ROOF PANELS
- WORK BEGINNING ON CENTER ENTRANCE FOR CANOPY
Week in Photos | 10/26 - 11/01
Share Week in Photos | Oct 19-25 on Facebook
Share Week in Photos | Oct 19-25 on Linkedin
Email Week in Photos | Oct 19-25 link
Share Week in Photos | Oct 11-18 on Facebook
Share Week in Photos | Oct 11-18 on Linkedin
Email Week in Photos | Oct 11-18 link
Share Phase I Update - September 2024 on Facebook
Share Phase I Update - September 2024 on Linkedin
Email Phase I Update - September 2024 link
Key Work Items Accomplished
- New terminal vehicle lane curbing installed.
- Pedestrian sidewalk placed and ready for concrete.
- New arrival/departure lanes graded and prepped for asphalt.
- EV charging stations (x2) site work complete.
- Steel structure for new TSA screening checkpoint area and exit lane 80% complete.
- Bioretention stormwater facility work 50% complete.
Important Coordinating Items
- Continue re-routing passengers through construction zones
- Demo remaining traffic lane and pave
- Approve interior graphics, light fixtures and accessories.
- Begin parking lot study and prep gate locations.
- Next big step will be framers inside new building.
Near-Term Look-Ahead
- PAVE 2 NEW ARRIVAL/DEPARTURE LANES
- POUR PEDESTRIAN SIDEWALK AND MAIN ENTRY WALKWAY
- COMPLETE SECTION 1 STEEL AND BEGIN SECTION 2
- INSTALL ROOF DECKING AND ROOF PANELS
- POUR FINAL SLAB ZONE 2
PROGRESS PHOTOS
Share Phase I Update - July 2024 on Facebook
Share Phase I Update - July 2024 on Linkedin
Email Phase I Update - July 2024 link
Key Work Items Accomplished
- Arrival and Departure lanes have been re-routed. Down to single lane.
- First 2 rows of parking spaces have been cleared and removed.
- All underground facilities have been installed, connecting the current facilities to the new terminal.
- 90% of the designed steel on site.
- Previously installed “dry” pond correction complete.
- Concrete colors/texture and window tinting approved.
Important Coordinating Items
- Arrange parking lot after lane paving to include handicap and new rental car locations.
- Traffic Control and night work monitoring.
- Approve interior graphics, light fixtures and accessories.
- Begin parking lot study and prep gate locations.
Near-Term Look-Ahead
- Complete arrival and departure lane facility work
- Pave new arrival/departure lanes
- Steel construction (going vertical)
- Pour final slab zone 2
PROGRESS PHOTOS
Underground Facilities Work
Dry Pond Correction
Arrival/Departure Traffic Lane Work
Final Footer Installation
Parking Space Demo
Share Phase I Update - June 2024 on Facebook
Share Phase I Update - June 2024 on Linkedin
Email Phase I Update - June 2024 link
Key Work Items Accomplished (April 22nd-June 6th)
- Surface wall installed and grouted
- Slab poured and cured (lower)
- Slab prep and grading complete (upper)
- Arrival/Departure lanes palm trees and shrubs removed
- Curbing for new entrance lane complete
- Underground facilities under entrance lane removed and reconfigured
Important Coordination Items
- Coordination with terminal tenants & customers for parking disturbances
- Parking and traffic flow impact for 2 to 4 months
- Website, social media updates
- Traffic Control and night work monitoring
- Summer season push – Airport Ambassadors on duty