Hilton Head Island Airport Terminal Improvements

Share Hilton Head Island Airport Terminal Improvements on Facebook Share Hilton Head Island Airport Terminal Improvements on Twitter Share Hilton Head Island Airport Terminal Improvements on Linkedin Email Hilton Head Island Airport Terminal Improvements link

Hilton Head Island Airport is thrilled to announce the commencement of Phase I of its Terminal Improvements Project, aimed at modernizing and enhancing the airport's facilities to meet the growing needs of passengers and the surrounding community. The project is spearheaded by the architecture firm The Wilson Group, headquartered in Charlotte, NC, and will be executed by Edison Foard. The contract, valued at $30,898,447.83, is projected to span two years and is funded through a combination of FAA Grants, SC Aeronautics Grants, State Funds secured by the local delegation and airport revenue.

For more information about the Hilton Head Island Airport, visit www.hiltonheadairport.com. For more information on this and other exciting Beaufort County projects, please visit www.beaufortcountysc.gov.

Hilton Head Island Airport is thrilled to announce the commencement of Phase I of its Terminal Improvements Project, aimed at modernizing and enhancing the airport's facilities to meet the growing needs of passengers and the surrounding community. The project is spearheaded by the architecture firm The Wilson Group, headquartered in Charlotte, NC, and will be executed by Edison Foard. The contract, valued at $30,898,447.83, is projected to span two years and is funded through a combination of FAA Grants, SC Aeronautics Grants, State Funds secured by the local delegation and airport revenue.

For more information about the Hilton Head Island Airport, visit www.hiltonheadairport.com. For more information on this and other exciting Beaufort County projects, please visit www.beaufortcountysc.gov.

  • Phase I Update - June 2024

    Share Phase I Update - June 2024 on Facebook Share Phase I Update - June 2024 on Twitter Share Phase I Update - June 2024 on Linkedin Email Phase I Update - June 2024 link
    supporting image
    Key Work Items Accomplished (April 22nd-June 6th)
    • Surface wall installed and grouted
    • Slab poured and cured (lower)
    • Slab prep and grading complete (upper)
    • Arrival/Departure lanes palm trees and shrubs removed
    • Curbing for new entrance lane complete
    • Underground facilities under entrance lane removed and reconfigured
      • Stormwater piping
    Important Coordination Items
    • Coordination with terminal tenants & customers for parking disturbances
      • Parking and traffic flow impact for 2 to 4 months
      • Website, social media updates
    • Traffic Control and night work monitoring

    • Summer season push – Airport Ambassadors on duty