Hilton Head Island Airport is thrilled to announce the commencement of Phase I of its Terminal Improvements Project, aimed at modernizing and enhancing the airport's facilities to meet the growing needs of passengers and the surrounding community. The project is spearheaded by the architecture firm The Wilson Group, headquartered in Charlotte, NC, and will be executed by Edison Foard. The contract, valued at $30,898,447.83, is projected to span two years and is funded through a combination of FAA Grants, SC Aeronautics Grants, State Funds secured by the local delegation and airport revenue.
For more information about the Hilton Head Island Airport, visit www.hiltonheadairport.com. For more information on this and other exciting Beaufort County projects, please visit www.beaufortcountysc.gov.
Hilton Head Island Airport is thrilled to announce the commencement of Phase I of its Terminal Improvements Project, aimed at modernizing and enhancing the airport's facilities to meet the growing needs of passengers and the surrounding community. The project is spearheaded by the architecture firm The Wilson Group, headquartered in Charlotte, NC, and will be executed by Edison Foard. The contract, valued at $30,898,447.83, is projected to span two years and is funded through a combination of FAA Grants, SC Aeronautics Grants, State Funds secured by the local delegation and airport revenue.
For more information about the Hilton Head Island Airport, visit www.hiltonheadairport.com. For more information on this and other exciting Beaufort County projects, please visit www.beaufortcountysc.gov.
Share Phase I Update - September 2024 on FacebookShare Phase I Update - September 2024 on TwitterShare Phase I Update - September 2024 on LinkedinEmail Phase I Update - September 2024 link
Key Work Items Accomplished
New terminal vehicle lane curbing installed.
Pedestrian sidewalk placed and ready for concrete.
New arrival/departure lanes graded and prepped for asphalt.
EV charging stations (x2) site work complete.
Steel structure for new TSA screening checkpoint area and exit lane 80% complete.
Bioretention stormwater facility work 50% complete.
Important Coordinating Items
Continue re-routing passengers through construction zones
Demo remaining traffic lane and pave
Approve interior graphics, light fixtures and accessories.
Begin parking lot study and prep gate locations.
Next big step will be framers inside new building.
Near-Term Look-Ahead
PAVE 2 NEW ARRIVAL/DEPARTURE LANES
POUR PEDESTRIAN SIDEWALK AND MAIN ENTRY WALKWAY
COMPLETE SECTION 1 STEEL AND BEGIN SECTION 2
INSTALL ROOF DECKING AND ROOF PANELS
POUR FINAL SLAB ZONE 2
PROGRESS PHOTOS
Key Work Items Accomplished
New terminal vehicle lane curbing installed.
Pedestrian sidewalk placed and ready for concrete.
New arrival/departure lanes graded and prepped for asphalt.
EV charging stations (x2) site work complete.
Steel structure for new TSA screening checkpoint area and exit lane 80% complete.
Bioretention stormwater facility work 50% complete.
Important Coordinating Items
Continue re-routing passengers through construction zones
Demo remaining traffic lane and pave
Approve interior graphics, light fixtures and accessories.
Begin parking lot study and prep gate locations.
Next big step will be framers inside new building.
Share Phase I Update - July 2024 on FacebookShare Phase I Update - July 2024 on TwitterShare Phase I Update - July 2024 on LinkedinEmail Phase I Update - July 2024 link
Key Work Items Accomplished
Arrival and Departure lanes have been re-routed. Down to single lane.
First 2 rows of parking spaces have been cleared and removed.
All underground facilities have been installed, connecting the current facilities to the new terminal.
Share Phase I Update - June 2024 on FacebookShare Phase I Update - June 2024 on TwitterShare Phase I Update - June 2024 on LinkedinEmail Phase I Update - June 2024 link
Key Work Items Accomplished (April 22nd-June 6th)
Surface wall installed and grouted
Slab poured and cured (lower)
Slab prep and grading complete (upper)
Arrival/Departure lanes palm trees and shrubs removed
Curbing for new entrance lane complete
Underground facilities under entrance lane removed and reconfigured
Stormwater piping
Important Coordination Items
Coordination with terminal tenants & customers for parking disturbances
Parking and traffic flow impact for 2 to 4 months
Website, social media updates
Traffic Control and night work monitoring
Summer season push – Airport Ambassadors on duty
Key Work Items Accomplished (April 22nd-June 6th)
Surface wall installed and grouted
Slab poured and cured (lower)
Slab prep and grading complete (upper)
Arrival/Departure lanes palm trees and shrubs removed
Curbing for new entrance lane complete
Underground facilities under entrance lane removed and reconfigured
Stormwater piping
Important Coordination Items
Coordination with terminal tenants & customers for parking disturbances