Key Work Items Accomplished
- Arrival and Departure lanes have been re-routed. Down to single lane.
- First 2 rows of parking spaces have been cleared and removed.
- All underground facilities have been installed, connecting the current facilities to the new terminal.
- 90% of the designed steel on site.
- Previously installed “dry” pond correction complete.
- Concrete colors/texture and window tinting approved.
Important Coordinating Items
- Arrange parking lot after lane paving to include handicap and new rental car locations.
- Traffic Control and night work monitoring.
- Approve interior graphics, light fixtures and accessories.
- Begin parking lot study and prep gate locations.
Near-Term Look-Ahead
- Complete arrival and departure lane facility work
- Pave new arrival/departure lanes
- Steel construction (going vertical)
- Pour final slab zone 2
PROGRESS PHOTOS
Underground Facilities Work
Dry Pond Correction

Arrival/Departure Traffic Lane Work

Final Footer Installation


Parking Space Demo



Share Phase I Update - June 2024 on Facebook
Share Phase I Update - June 2024 on Linkedin
Email Phase I Update - June 2024 link
Key Work Items Accomplished (April 22nd-June 6th)
- Surface wall installed and grouted
- Slab poured and cured (lower)
- Slab prep and grading complete (upper)
- Arrival/Departure lanes palm trees and shrubs removed
- Curbing for new entrance lane complete
- Underground facilities under entrance lane removed and reconfigured
Important Coordination Items
- Coordination with terminal tenants & customers for parking disturbances
- Parking and traffic flow impact for 2 to 4 months
- Website, social media updates
- Traffic Control and night work monitoring
- Summer season push – Airport Ambassadors on duty